Data Table for Joint Road Improvement Agreement for the Reconstruction of a portion of South Grove Road | ||||
Task Name | Task Status | Assigned To | Start Date | End Date |
---|---|---|---|---|
Initial Discussions & Planning | New Item | 04/02/2012 | 11/09/2012 | |
MDOT submitted Type, Size, & Location | New Item | 12/14/2012 | 12/14/2012 | |
MODT Program application | New Item | 01/11/2013 | 01/11/2013 | |
Status Update Meeting | New Item | 01/22/2013 | 01/22/2013 | |
MDOT Submit Acceptable GL package | New Item | 01/25/2013 | 01/25/2013 | |
MDOT Approx GI Date | New Item | 02/22/2013 | 02/22/2013 | |
MDOT Row Cert, permits, final plans, proposal & Est to LAP | New Item | 03/29/2013 | 04/11/2013 | |
MDOT Requested revisions to LAP | New Item | 04/12/2013 | 06/07/2013 | |
MDOT Letting date | New Item | 06/07/2013 | 06/07/2013 | |
Approved by Ypsilanti City Council | New Item | 11/12/2013 | 11/12/2013 | |
Approved by Ypsilanti Township Board of Trustees | New Item | 11/20/2013 | 11/20/2013 | |
Joint Road Improvement Agreement Signed | New Item | 11/20/2013 | 11/20/2013 | |
Expect reimbursement from City | New Item | 11/29/2013 | 11/29/2013 |