Data Table for Ypsilanti Township Park and Ride | ||||
Task Name | Task Status | Assigned To | Start Date | End Date |
---|---|---|---|---|
MDOT completed the Environmental Study for Project Classification | New Item | 08/01/2012 | 08/24/2012 | |
DTE submitted letters to MDOT to meet the requirements. | New Item | 10/01/2012 | 10/31/2012 | |
MDOT approved DTE Documentation | New Item | 01/04/2013 | 01/04/2013 | |
Start Installation Project | New Item | 03/01/2013 | 06/30/2013 | |
Complete Project | New Item | 06/30/2013 | 06/30/2013 |