Data Table for Hart City Hall Facility Upgrade | ||||
Task Name | Task Status | Assigned To | Start Date | End Date |
---|---|---|---|---|
Correct water drainage problems | New Item | 08/01/2012 | 09/28/2012 | |
Remove & upgrade stoop to ADA standards | New Item | 09/04/2012 | 09/28/2012 | |
Construct interior partition | New Item | 12/03/2012 | 12/21/2012 | |
Paint interior walls | New Item | 02/04/2013 | 02/22/2013 | |
Restroom upgrade | New Item | 02/04/2013 | 04/17/2013 | |
Replace double doors with ADA accessible | New Item | 02/20/2013 | 02/27/2013 | |
Tile walkway, entry way, restroom | New Item | 03/23/2013 | 04/03/2013 | |
Install projection screen | New Item | 04/01/2013 | 04/02/2013 | |
Place interior carpet | New Item | 04/08/2013 | 04/12/2013 | |
Install ceiling mount projector | New Item | 04/30/2013 | 05/30/2013 | |
Install sound system | New Item | 04/30/2013 | 05/30/2013 |